Taryan Towers’ Third Tower Is Under Active Construction

Construction of the third tower of Taryan Towers is actively progressing across several areas.

Glazing works are currently underway on the 33rd and 34th floors, while the SkyWalk structures have already been prepared for the next stage — concreting. Roof construction works are also progressing in parallel.

Work continues on the complex’s key infrastructure and lifestyle spaces. Final finishing works are underway at the panoramic restaurant, along with preparations for the installation of technical equipment. The premium supermarket is also being fitted out, while the painting of the access roads has been completed.

At the SPA by TSARSKY, installation works and reinforcement of the covered area’s floor slab are ongoing.

The third tower of Taryan Towers is steadily moving closer to completion, together with the spaces and infrastructure that shape a fully integrated, world-class lifestyle complex.